Quotation MarksTwo deliverables were provided to our client including an Environmental Management System audit report and an ISO 14001 Gap Analysis report.

Client: Alterra Power Corp / Toba Montrose General Partnership

Location: Powell River, BC

Date: 2014 – 2015

Project Lead: Greg Quandt

Project Team: Mary Smulders, Lara Raimondi

HYDROELECTRIC PROJECT EMS AUDIT AND GAP ANALYSIS

Overview
An Environmental Management System (EMS) audit and gap analysis was conducted for a 235 megawatt run-of-river development on the East Toba River and Montrose Creek located north of Powell River, BC. The project involved conducting an audit to assess project conformance with its EMS, assessing the effectiveness of the internal audit process, and providing a gap analysis of the existing EMS against the ISO 14001:2004 standard.

Approach
The objective of the EMS audit was to provide an independent assessment of project conformance with Toba Montrose General Partnership’s (TMGP) EMS and determine the effectiveness of the internal audit process. The EMS audit involved:

  • Planning and Preparation: Set and review audit scope, objectives, and criteria; review of audit plan; identify environmental issues to be assessed; identify audit procedures to be used; identification of interviewees; document review, update internal audit criteria table, and familiarization with project operations
  • Audit: Opening and closing meeting; introductions to facility staff; review of EMS documentation kept on-site; facility walk-through; interviews; audit project conformance to EMS using updated audit table; closing meeting and debrief
  • Reporting: Completion of audit report which included a description of the project scope and methodology, project limitations, evaluation and discussion, and an updated internal audit criteria table

Results
Two deliverables were provided to our client including an EMS audit report and an ISO 14001 Gap Analysis report. The EMS audit report included the above noted points and updated audit criteria table which identified conformance, non-conformances, and opportunities for improvement. An assessment of the current audit process was also included in the report.

HYDROELECTRIC PROJECT EMS AUDIT AND GAP ANALYSIS

Client: Alterra Power Corp / Toba Montrose General Partnership
Location: Powell River, BC
Date: 2014 – 2015
Project Lead: Greg Quandt
Project Team: Mary Smulders, Lara Raimondi

Overview

An Environmental Management System (EMS) audit and gap analysis was conducted for a 235 megawatt run-of-river development on the East Toba River and Montrose Creek located north of Powell River, BC. The project involved conducting an audit to assess project conformance with its EMS, assessing the effectiveness of the internal audit process, and providing a gap analysis of the existing EMS against the ISO 14001:2004 standard.

Approach

The objective of the EMS audit was to provide an independent assessment of project conformance with Toba Montrose General Partnership’s (TMGP) EMS and determine the effectiveness of the internal audit process. The EMS audit involved:

  • Planning and Preparation: Set and review audit scope, objectives, and criteria; review of audit plan; identify environmental issues to be assessed; identify audit procedures to be used; identification of interviewees; document review, update internal audit criteria table, and familiarization with project operations
  • Audit: Opening and closing meeting; introductions to facility staff; review of EMS documentation kept on-site; facility walk-through; interviews; audit project conformance to EMS using updated audit table; closing meeting and debrief
  • Reporting: Completion of audit report which included a description of the project scope and methodology, project limitations, evaluation and discussion, and an updated internal audit criteria table

An EMS gap analysis was conducted to complete an independent assessment of TMGP facility EMS to identify where the EMS conforms with the ISO14001:2004 standard and to identify non-conformances, corrective actions and/or opportunities for improvement, and to provide recommendations.

Results

Two deliverables were provided to our client including an EMS audit report and an ISO 14001 Gap Analysis report. The EMS audit report included the above noted points and updated audit criteria table which identified conformance, non-conformances, and opportunities for improvement. An assessment of the current audit process was also included in the report.